Excavation FLHA template for Canadian worksites
An excavation field-level hazard assessment (FLHA) is the crew's check of the ground, buried services, protection and people at the exact dig location before work starts. Use the form below alongside the formal excavation plan, current utility locates, any required permit and the protective-system design. Stop if the conditions in the field differ from those documents. A signed FLHA does not make an unsupported trench safe or give permission to disturb ground.
This is a Canadian template, not a claim that every province uses the same excavation limits. CCOHS explains that soil classifications and protective requirements vary by jurisdiction. Alberta, for example, has a detailed OHS Code Part 32 on excavating and tunnelling covering soil classification, buried facilities, water, protective methods and access. Select the law and site rules that actually apply before using this form. Where the excavation crosses a utility easement, roadway, occupied site or another employer's work area, include the owner and coordination requirements too.
Excavation job identification
| Field | Site-specific entry |
|---|---|
| Project, employer, prime contractor and permit number | |
| Exact dig location, chainage/coordinates and marked limits | |
| Date, time, crew, supervisor and competent excavation lead | |
| Task today: locate, expose, trench, enter, install, backfill or inspect | |
| Excavation depth, width, length and planned worker entry | |
| Current approved drawings, utility locates and expiry/refresh conditions | |
| Soil/ground assessment and protective-system plan reference | |
| Nearby structures, roads, pedestrians, other trades and public boundary | |
| Emergency contact, access route and rescue arrangements |
Mark a changed or unknown field HOLD, not “to be confirmed”. The crew should be able to point to the marked services and the controlled work boundary. A drawing alone is not proof that all facilities have been located at the workface. The locate record may have geographic, depth, validity or tolerance limits that need checking with the utility owner and the applicable ground-disturbance procedure.
Before-dig field checks
| Check at the actual workface | Observation/evidence | Action, owner and release decision |
|---|---|---|
| Current utility-owner responses and marked buried services | ||
| Overhead lines, equipment clearance and isolations | ||
| Soil type, fill, previously disturbed ground, fissures or sloughing | ||
| Water, seepage, rain, freeze/thaw and forecast | ||
| Adjacent foundations, pavement, poles, traffic and vibration | ||
| Slope, shoring, shielding or other approved protection | ||
| Protective equipment installed and inspected as designed | ||
| Spoil, materials and equipment loading near the edge | ||
| Barricades, pedestrian separation and falling-object exposure | ||
| Access/egress and whether entry is planned | ||
| Atmospheric hazard assessment and required testing | ||
| Plant condition, operator authorisation and spotter communication | ||
| Emergency response and how work will be stopped |
CCOHS identifies cave-ins, falling soil or equipment, falls, water, hazardous atmospheres, buried services and mobile equipment as excavation hazards. The CCOHS trenching and excavation guide also recommends checking conditions before excavation and during inspections. The table is a prompt to observe and verify, not a substitute for the jurisdiction's detailed technical requirements. Do not copy a numerical spoil setback, depth trigger or slope ratio from another province into a live plan without checking the applicable law and engineering advice.
Utility locate and exposure gate
Identify the owner of every possible buried facility, obtain the required locates, check marks and site information against the planned dig, and agree the method of exposure and clearance. Locate marks can be disturbed by traffic, weather or other work. If the crew finds an unidentified line, unexpected fill or a mismatch between drawings and the ground, stop mechanical digging, secure the area and escalate to the utility owner and site authority. Do not improvise a clearance distance from memory. Alberta Part 32 has specific rules for locating and exposing buried facilities; the actual site may be governed by different law and utility conditions.
Ground-stability and entry gate
Record whether workers will enter. Confirm the competent person's assessment of the ground and the protective method selected for the current depth, width, soil, water, vibration and adjacent loads. Check that the shoring, shield, sloping or other measure is installed and suitable for the conditions actually present. A trench box is a protective system with limits, not permission to ignore unsupported ground outside it. CCOHS distinguishes trench boxes from systems that support the trench wall. No one enters merely because the form is signed. Entry requires the applicable legal protections, safe access/egress and the site's release process.
Water can make a previously stable excavation unsafe. So can new vibration from a nearby road or compaction plant, a spoil pile moved towards the edge, or a changed excavation profile. Stop, withdraw people and have the protective plan reconsidered when these conditions change. A field card should document the change and the decision maker; it cannot redesign the protection.
Plant and people gate
Define where excavators, trucks and pedestrians travel. Keep workers clear of moving buckets and suspended loads; control reversing and blind spots with separation and the approved communication method. Check edge stability before placing plant near it. Protect the public and other trades from falls into the opening and from falling material. Identify the person coordinating interfaces between employers. High-visibility clothing may help detection but does not replace a suitable barrier or traffic plan.
Task-step hazard and control record
| Today's step | Hazard and person exposed | Control verified in place | Missing control/action owner | GO / HOLD |
|---|---|---|---|---|
| Mark and set out the dig | ||||
| Expose and protect buried facilities | ||||
| Excavate and move spoil | ||||
| Install or adjust protection | ||||
| Enter and perform work, if authorised | ||||
| Backfill, remove protection and hand back |
Use observable controls. “Utilities located under current ticket and potholes completed to the utility owner's method” is a more useful entry than “watch for services”. “Protective system installed to approved plan and inspected by named competent person” is more useful than “trench box on site”. If a step needs a specialist, utility owner, engineer or permit issuer to release it, name that person and capture the evidence. The employer's formal hazard assessment and protective design remain the controlling documents.
Hold and change log
| Trigger | Required decision or evidence | Owner/time |
|---|---|---|
| Unmarked or damaged buried facility | Stop, isolate/secure as appropriate, contact owner and revise method | |
| New seepage, rain, sloughing or soil change | Withdraw people; competent ground/protection review | |
| Protective system missing, damaged or changed | No entry until approved system restored and verified | |
| New adjacent load, roadwork or vibration | Reassess edge and ground stability | |
| Suspected hazardous atmosphere | No entry until assessment/testing and controls under applicable law | |
| Loss of access, barricade or plant separation | Restore protection and rebrief affected people |
The person who discovers the condition records when work stopped and whom they told. The authorised lead records the revised plan or permit reference, installed control, independent verification where required, crew briefing and time of release. “Supervisor informed” by itself is not a release. If the site's emergency plan calls for a specialist rescue response, do not send an unprotected coworker into a collapse or hazardous atmosphere.
Crew review and worked example
| Confirmation | Name, time and evidence |
|---|---|
| Crew reviewed the dig limits, locates and protection | |
| Other employers and utility owners were coordinated with | |
| Everyone knows who can stop work and who can release it | |
| Access, emergency route and communication were checked | |
| Conditions needing a new FLHA or plan review were agreed |
Example: A crew plans to open a service trench beside a delivery road. The utility locate and trench protection plan were completed the previous day. Overnight rain leaves standing water and a delivery contractor begins parking trucks near the excavation edge. The crew records those differences and marks the dig HOLD. The competent person reviews soil and water conditions, the site lead moves the delivery route and confirms edge loading, and the protective system is checked against the revised situation. The crew is rebriefed before any authorised entry. The FLHA documents that sequence; it does not decide the design by itself.
Review the FLHA before a new task stage, after a shift or crew change, and whenever ground, weather, utilities, plant, nearby work or protection changes. Update the formal assessment, permit or design when the change exceeds the field card's scope. Retain the completed record according to the site's and jurisdiction's rules.
Related Complys resources
The Canadian hazard-assessment guide covers how hazard assessment works. The Canadian tools directory lists related tools. This page provides the narrower blank excavation workface form with locate, protection, entry and hold/release fields. If you are evaluating software: Ask Complys to show how your current excavation hazard records and follow-up actions could be organised for your team. Finding buried services, selecting trench protection, granting entry and verifying engineering remain with the employer and competent persons.
Sources
- National hazard overview and jurisdiction variation: CCOHS trenching and excavation
- Alberta example for ground, services, protection, water and access: Alberta OHS Code Part 32
- Related Complys pages: CA general hazard guide, CA tools