Complys IE → Templates → Construction stage safety and health plan template for Ireland
Templates

Construction stage safety and health plan template for Ireland

A construction-stage safety and health plan is a project-specific working plan developed by the project supervisor for the construction stage (PSCS) before construction starts where the Irish Construction Regulations require it. Use the blank framework below to organise the real project information, particular risks, site rules, contractor coordination and updates. It is not a substitute for the PSCS's judgement, the preliminary plan from the project supervisor for the design process (PSDP), contractors' own assessments, or the actual controls on site.

The Health and Safety Authority (HSA) advises the appointed PSCS to develop a suitable construction-stage plan before work begins, build on the PSDP's preliminary plan, make it specific to the job and keep it current. S.I. No. 291/2013, regulation 16 sets the relevant PSCS plan duties; its amended text and the project's exact trigger should be checked. The HSA also provides an official template. This Complys framework is an original planning worksheet organised for handover and change control, not an HSA form or a legal certificate.

For an overview of who appoints whom and when, the existing Irish Construction Regulations guide owns that intent. This page is for someone who needs to fill out and maintain a plan. Do not confuse it with a UK Construction Phase Plan under CDM 2015 or with a contractor's task RAMS.

Before you fill it out

The PSCS should have the written appointment, the PSDP's preliminary safety and health plan where required, design information, existing drawings and safety file, site/utility/asbestos information, planned sequence and known contractor scopes. The client should provide relevant information and make the required appointments; the HSA's client duties page explains that role. If significant information is missing, record a hold point and owner rather than filling a blank with “N/A”. Competent designers, temporary-works engineers, utilities or other specialists may need to resolve issues before a method is authorised.

Copyable plan framework

Copy the sections into a controlled document. Add or remove sections to match the project, but retain a clear decision trail for omitted items.

A. Document control and appointments

FieldProject entry
Project / site / address[Name and precise location]
Client and contact[Name / role / contact]
PSDP and written appointment reference[Organisation, named contact, document/date]
PSCS and written appointment reference[Organisation, named contact, document/date]
Lead designers / principal contractors / key trades[Names, roles, contact route]
Planned start, stages and completion[Dates; assumptions]
Plan owner and approval[PSCS person / sign-off date]
Version, issue date and next review trigger[Version / date / trigger]
Preliminary plan received and reviewed[Source/version, gaps, hold points]
HSA notification assessment[Applicable? basis, responsible person, date/reference if submitted]
Safety file / design information location[Controlled location and access]

Stop gate: Do not start an affected activity merely because a name appears in this table. Check that relevant dutyholder appointments, competence and resources are in place, and that the necessary site information and controls are available. The plan does not make an unappointed or incompetent party a PSCS.

B. Project scope, sequencing and interfaces

Describe the works in plain language: [scope]. Identify stages: [enabling], [demolition/alteration], [groundworks], [structure], [services], [finishes], [commissioning], [handover]. State occupied areas, shared access, neighbouring premises, public interfaces and any areas excluded from contractor control. Attach a marked-up site plan. For each phase, note concurrent trades and access changes; an apparently safe method can fail when two teams work in the same zone.

Stage / dateMain activities and contractorInterface or constraintCoordination owner / hold point
[Stage][Work and team][Other team, public, services, existing operation][Name / approval]
[Stage][Work and team][Interface][Name / approval]

C. Particular risks and design information

Transfer significant design-stage information from the PSDP and review it against the actual construction sequence. The 2013 Regulations include a schedule of particular risks. Consider, as applicable, work at height or near fragile surfaces; burial or excavation; asbestos; live electrical or other services; drowning; heavy prefabricated elements; confined or contaminated spaces; demolition; temporary works; lifting; public/traffic interface. This list is a prompt, not proof that every listed item applies or that unlisted hazards are absent.

Particular risk / locationSource of informationDesign/engineering controlConstruction control and competent ownerResidual risk / hold point
[Risk][Drawing, survey, preliminary plan][Avoid, redesign, isolate][Method, permit, inspection, named person][What must be verified before start]
[Risk][Source][Control][Control/owner][Hold point]

For example: If an existing roof may be fragile, the plan should identify the roof section, survey evidence, how access will be prevented until a safe system is designed, fall prevention and rescue arrangements. “Working at height — wear harness” is not a sufficient project-specific plan.

D. Site set-up and common arrangements

ArrangementAgreed project control / record
Site boundary, public protection and signs[Drawing, barriers, checks]
Access, delivery booking and traffic/pedestrian separation[Route and supervisor]
Welfare, drinking water and sanitary facilities[Location and responsible party]
First aid, emergency contact, ambulance access and rescue[Names, location, tested route]
Fire prevention, alarm, evacuation and assembly[Plan and drills/briefing]
Underground/overhead services and isolation[Survey, permit and authorised sign-off]
Materials, waste, hazardous agents and storage[Control and owner]
Plant, lifting equipment and temporary works[Design/inspection/authorisation record]
Weather, lighting and out-of-hours controls[Trigger and stop rule]
Occupied-building or neighbour coordination[Communication and protection]

Show which arrangement is a project-level control and which belongs in a contractor's task-specific risk assessment/method statement. A site map, logistics plan, emergency plan and contractor RAMS may be referenced as controlled attachments rather than pasted into every version.

E. Site rules and access conditions

Write the actual rules for this site, not a copied slogan sheet. Examples to decide and document: induction before entry; access and visitor escort; mandatory PPE by zone; permit-to-work areas; work at height and open edge restrictions; traffic routes; lifting exclusion zones; hot work; excavation entry; service isolation; housekeeping; reporting hazards/incidents; stop-work authority; emergency signal and assembly. State who communicates each rule and how a changed rule reaches every affected crew. The HSA offers site rules and induction resources.

Rule or restricted activityApplies to whom/whereBriefing or authorisation evidenceEnforcement / review owner
[Rule][People/area][Induction/permit/briefing][Name]

F. Contractor coordination and safe work

Set a practical sequence: receive scope and competence evidence; obtain task RAMS and specialist design/permits; check interfaces; brief the workforce; verify controls on site; monitor changes; stop and reassess if the method no longer matches work. The Construction Regulations put cooperation and information duties on contractors as well as the PSCS. The PSCS's plan should state how contractors share site-specific information and how simultaneous operations are resolved. A signed RAMS is evidence of communication, not proof that a scaffold, excavation, isolation or lifting set-up is safe.

Contractor / activityInformation and method requiredInterface checkAuthorised by / dateChange trigger
[Name/work][RAMS, design, permit, card/competence][Conflict and control][Person/date][Trigger]

G. Inspections, incidents and changes

List the inspections needed for the particular site and who receives findings. Record how accidents/dangerous occurrences are reported to the PSCS and, where legally required, to the HSA through the correct official route. A project register should track open actions, not just completed forms.

Event or changeImmediate actionPlan/RAMS update?People to briefClose-out evidence
New contractor or activity[Pause interface work, assess][Version/owner][Teams][Record]
Design or sequence change[Review risks and controls][Decision][Teams][Approval]
Incident, near miss or failed control[Make safe, investigate][Review][Teams][Corrective action]

Maintain a version history: [version], [change], [reason], [approved by], [date], [distribution]. Put a hold on work whose safe method depends on an unapproved change. The HSA says the plan should be kept updated and relevant information made available to people associated with the project who need it.

H. Completion and safety-file handover

Before demobilisation, record residual risks, as-built information, relevant equipment/structure details, testing and inspection records, and outstanding actions for the PSDP's safety file where applicable. The safety file is different from the construction-stage plan: it supports safe future maintenance, repair, alteration or demolition. Record who receives each item and when, rather than stating “safety file complete” with no evidence. The HSA safety-file guidance explains its future-work purpose.

A worked change example

A fit-out project plans overhead services above an occupied corridor. The initial plan provides out-of-hours access and segregation. Midway through, the client asks for daytime work and a new contractor brings a mobile elevating work platform. The PSCS should not simply add the contractor's RAMS to the folder. It should check corridor access, fire escape, ground/loading, platform selection, isolation, exclusion below, emergency lowering and the occupants' revised route; coordinate with the client and designer where needed; change the plan and site rules; brief every affected team; and record the authorisation before work restarts. That is how a construction-stage plan stays a live coordination tool.

Common mistakes to avoid

  • Using a UK CDM Construction Phase Plan with “principal designer/principal contractor” labels on an Irish project without adapting the legal roles and duties.
  • Copying the HSA or supplier template unchanged; a good format is only a starting point.
  • Treating the client's preliminary plan and the PSCS's construction-stage plan as the same completed document.
  • Listing hazards without controls, competent owners, hold points or a way to test them.
  • Leaving temporary works, lifting, services or asbestos as generic “contractor to manage” statements.
  • Putting personal medical or confidential information into a plan circulated to everyone; keep incident case records separately controlled.
  • Marking a plan approved once and failing to update it after changes in design, sequence, contractors or site conditions.

Complys and next step

The Irish construction compliance page describes a commercial context for organising safety records, RAMS, staff evidence and project information. Verify the current Irish implementation before saying it creates a statutory construction-stage plan, automatically validates PSDP/PSCS appointments or fulfils the PSCS's legal duties. The plan must be prepared and maintained by competent project dutyholders. If your team uses software, test whether it can maintain controlled versions, role access, action owners and attachments for the real project.

Next step: obtain the PSDP information, appoint and confirm the PSCS where required, then work through this framework with the actual site team. Use the HSA's current construction-stage plan guidance to check the result before work begins.

Source and claim register — checked 5 October 2026

Material claimPrimary source and boundary
Irish roles and plan dutiesS.I. 291/2013 as amended, especially regs 6, 9, 12, 16–17 and relevant schedules; verify current consolidated/amendment position and exact project trigger.
PSCS construction-stage plan before work and site-specific updatesHSA construction-stage plan guidance; the HSA has its own template.
Client information and appointmentsHSA client duties.
Domestic-project plan form is not itself statutoryHSA guide for contractors, appendix; this worksheet is likewise a format, not approval.
Safety file purposeHSA safety-file guidance.