A scaffolding RAMS in Ireland should define the scaffold's purpose and configuration, verify design and ground support, plan safe delivery, erection, alteration and dismantling, control falls and falling objects, record inspection and handover, and specify who can authorise changes. This fillable template is a decision record for a competent scaffolding contractor. It is not a scaffold design, an inspection certificate or permission for an untrained person to erect a scaffold.

Use the Health and Safety Authority (HSA) Code of Practice for Access and Working Scaffolds as the primary Irish technical source, alongside the HSA's RAMS guidance and current RAMS/Safe Plan of Action approach. The HSA code explains why delivery, erection, use and dismantling each need risk assessment, design, suitable equipment, training, supervision and checking. UK TG20, SG4, CDM 2015 and LOLER references from a UK marketing page do not replace the applicable Irish rules or an Irish site design.

Decide what the scaffold must do

Name the users and work: façade repair, roof access, cladding, brickwork, temporary edge protection or another task. Record the intended platform levels, loads, material storage, access, spans, sheeting/netting and tie/anchor positions. Check ground capacity, basements/voids, adjacent structures, overhead lines, vehicle routes and public footpaths. Any unusual geometry or increased wind loading from sheeting needs a competent design decision. A scaffold is a temporary structure; adding a hoist, moving a tie, removing a guardrail or stacking more materials can invalidate the design and handover.

Identify the scaffold's design basis and limits before a tube is unloaded. Who checked it? Which drawings/revisions apply? How will users know the permitted loading and unavailable lifts? Who is responsible for inspecting the scaffold before handover, during use and after alteration or severe weather? Record these decisions in the RAMS and the project safety arrangements. Do not write “scaffold inspected” without a named competent person, record and condition.

Copyable scaffold RAMS worksheet

Replace every bracket with site evidence. Mark an unknown design, service, access or inspection item HOLD rather than guessing.

A. Project and document control

FieldSite-specific entry
Project, address and precise scaffold location[ ]
Client, PSCS/site coordinator and scaffold contractor[Names and contact details]
Purpose, users, tasks and platform levels[ ]
Scaffold type, system and manufacturer instructions[ ]
Design drawing/calculation or approved configuration reference[Designer, checker, revision, design limit]
Loading class/intended material load and prohibited changes[As determined by designer]
Ground, foundations, basements and underground-service information[ ]
Ties/anchors, sheeting, netting, bridges, hoists and public protection[Design references]
Overhead electricity and other site interfaces[ ]
Delivery, erection, use, alteration and dismantling dates[ ]
Inspection/handover record and permit references[ ]
RAMS author, reviewer, approver and version[ ]

Hold A — design and site: a competent person must confirm the scaffold design, ground bearing, tie/anchor strategy, loading and interfaces. If the site cannot accept the planned scaffold or a road/footpath requires permission, redesign or obtain approval before erection. A general RAMS cannot certify the ground, façade or anchor.

B. People, competence and equipment

The HSA CSCS guidance lists basic and advanced scaffolding and mobile tower scaffold tasks, with nuanced exceptions for some mobile towers. Check the actual activity and current scheme criteria; do not assume the same card is needed for every platform or that Safe Pass alone is sufficient. The employer still has to provide appropriate instruction, training and supervision.

Role or itemPerson/IDRequired competence/design/inspection evidenceVerified by/date
Scaffold supervisor[ ][Experience, task qualification, authority][ ]
Erection/alteration/dismantling crew[ ][Relevant current CSCS/training for task][ ]
Scaffold designer/checker[ ][Competent design and revision approval][ ]
Inspection/handover competent person[ ][Current role and form/process][ ]
Lift/telehandler operator and signaller, if used[ ][Relevant competence and lifting plan][ ]
System components, access and fall-prevention equipment[ ][Suitable, inspected, compatible, not damaged][ ]

Record how new workers are briefed, who may direct alterations and who may remove a red/closed status. The HSA code gives priority to collective safeguards such as adequate platforms and guardrails, with other fall protection where that is not practicable. Never use a harness as a generic replacement for planned safe erection or a rescue arrangement. The scaffold contractor's actual system instructions and design set the detailed assembly method.

C. Erection, use and dismantling work stages

Use this as a framework. The competent contractor must add lift-by-lift details, design checks, permits and hold points. No one should use a partly erected or altered scaffold as if it had been handed over.

StageMain hazard / exposed peopleRequired site-specific control and verificationOwner
Delivery and unloadingVehicle strike, falling components, manual handling, publicControlled delivery slot/route, unloading plan, secure laydown, public/crew segregation[ ]
Ground/base preparationSettlement, void, buried service, slopeCompetent ground assessment, designed base and exclusion; verify before loading[ ]
Initial frames/standardsFall, instability before ties, dropped componentsApproved erection sequence, suitable working platform/collective protection, controlled component raising and exclusion below[ ]
Tie/brace/platform progressionIncomplete stability, overloaded temporary stageFollow design/sequence and inspection; no omitted tie, brace, deck or guardrail without approved alternative[ ]
Access, edge and falling-object protectionFalls of people/materials, unauthorised entryDesigned stairs/ladders, guarded edges/openings, toe/other protection, controlled entry and public shield[ ]
HandoverScaffold used before completion or inspectionCompetent inspection, defects closed, load/use limits communicated, handover record accepted by site[ ]
Use and routine inspectionOverload, tampering, weather damage, altered tieUser instruction, no unauthorised change, named inspection process/record, withdraw from use on defect[ ]
AlterationLoss of stability or protectionStop use in affected area, competent revised design/method, reinstall protection, reinspect and re-handover[ ]
Dismantling/loadingFall, premature tie removal, falling items, public riskDesigned reverse sequence, exclusion and load control, protect remaining structure and site[ ]

Hold B — before use or after change: the responsible person must confirm the scaffold matches the approved design and the inspection/handover record is current. Users may not remove ties, rails, boards or other elements for convenience. If a tie is unavailable because of façade work, a designer must provide the alternative. Storm damage, vehicle impact, unplanned loading or ground movement triggers immediate isolation and competent inspection/reassessment.

D. Site-specific interfaces and decisions

Ground and foundations. Check paving, soil, underground services, basements, trenches and adjacent excavations. Do not assume a solid-looking surface has enough bearing capacity. Record any designed spreader or foundation requirement and how it will be inspected throughout use. A separate groundworks plan may be necessary.

Power lines and live services. The HSA code identifies contact with overhead electric lines as a major life-threatening hazard. Locate lines before erection and lifting, obtain the owner's advice and agree appropriate isolation, clearance or alternative location. A spotter alone cannot make a dangerous clearance safe.

Public and traffic. A scaffold beside a footpath or road needs a physical exclusion, protected pedestrian route, impact protection and any relevant authority permission. Delivery and dismantling can create greater public exposure than routine use. Record when access must be closed and who controls it.

Weather and sheeting. Sheeting, netting and banners change wind load. The designer must account for them. Set inspection and stop-work triggers from the actual design and manufacturer information, not an arbitrary weather number. High wind, ice or lightning may make erection or use unsafe; the supervisor secures the area and reassesses.

Access and rescue. Specify safe access to every authorised lift and how anyone who falls or becomes injured will be reached without exposing rescuers to the same danger. If a personal fall system is used, verify anchor, clearance, compatibility, trained users and prompt rescue. A note saying “call emergency services” is insufficient as the entire rescue method.

Interface/permitEvidence and approvalHold point / owner
Ground/foundation and adjacent excavation[ ][ ]
Overhead lines and services[ ][ ]
Road/footpath/public protection[ ][ ]
Façade anchors and ties[ ][ ]
Sheeting, hoist, bridging and altered loading[ ][ ]
Work at height/rescue, lifting and weather[ ][ ]

E. Inspection, communication and emergency record

The HSA Code of Practice for Access and Working Scaffolds covers design, erection, inspection, use and dismantling. The HSA CSCS FAQ refers to the work-at-height inspection regime, including inspection of a working platform from which a person could fall 2 m or more within the previous seven days. Exact frequency and form depend on equipment, task and applicable regulations; a competent Irish specialist must review the current law and the project inspection plan. The HSA RAMS template lists GA3 as an equipment examination/inspection record prompt. Do not mistake the presence of a GA3 checkbox for a complete scaffold inspection or a universal one-size schedule.

Inspection or communicationPerson/date/location of record
Component checks before use[ ]
Initial design/erection inspection and handover[ ]
Routine statutory/site inspections and GA3 where applicable[ ]
After alteration, impact, weather or suspected defect[ ]
Load limits, unavailable lifts and user brief[ ]
Daily scaffold crew SPA/brief and public interface check[ ]
Dismantling permit and post-removal site condition[ ]

Emergency triggers: fall, dropped component, platform instability, vehicle impact, electric-line proximity/contact, fire, severe weather or unexpected ground movement. Stop and isolate the scaffold, protect the area below, call emergency services where necessary and seek competent structural/electrical assessment before re-entry. Do not send an untrained colleague onto an unstable platform for rescue. Record the assembly point, access for responders and nominated coordinator.

Change control: any move of ties, boards, guardrails, loading, hoists, sheeting or intended user activity requires a competent design/plan decision, a revised RAMS and a new handover/inspection as needed. A verbal client request does not authorise alteration. The supervisor records who approved the change and briefs both the scaffold crew and users.

Worked example: façade scaffold beside a shop entrance

A shop remains open while a scaffold is erected for façade repairs. The proposed design needs standards near a pedestrian entrance, ties to a wall with uncertain substrate, and sheeting to contain dust. The RAMS must identify the actual design and anchor assessment, obtain a protected temporary customer route and delivery window, control overhead electrical services, and account for the sheeting's wind load. Erection may need to pause while the entrance is closed; a barrier that still lets customers walk under loose components is not enough. After erection, a competent person inspects and hands over the scaffold with load/use restrictions. If the façade team later asks to remove a tie for masonry work, the affected area is taken out of use until the scaffold designer approves a substitute and it is installed, inspected and communicated. The lesson is that scaffold safety runs through design, erection, use and alteration, not just a pre-start signature.

Common errors

  • Copying a UK TG20/SG4 marketing checklist as the Irish legal basis. Use current HSA code and Irish regulations; the system manufacturer/design may add technical requirements.
  • Leaving ground capacity and tie positions to be “decided on site.” These are design inputs and hold points.
  • Assuming Safe Pass equals scaffolder competence. Check CSCS task categories and actual experience.
  • Using the scaffold before a recorded competent handover or after an undocumented alteration. Segregate and re-release it.
  • Ignoring delivery and dismantling exposure. The public and other trades can be struck before or after routine platform use.
  • A harness with no compatible anchor or rescue. Collective protection and planned safe erection come first.
  • Treating inspection as a green tag only. Record competent findings, defects, corrective action and the condition of the actual scaffold.

Links and Complys boundary

The live Irish construction compliance guide remains the broad information owner. This is a distinct fillable Irish scaffolding work-package template. The observed Irish construction sector page is a potential money link after implementation/commercial verification. The UK scaffolding RAMS page must not be used as Irish product/legal proof, and the proposed /ie/rams-software route was not verified live. Do not claim Complys designs scaffold, assigns load classes, validates CSCS or signs GA3. A future CTA may invite a demo of implemented document, expiry, revision and handover storage only if tested.

Source/claim and writer-side QA register — 5 October 2026

Claim/checkCurrent primary evidenceDisposition / publication gate
Scaffold design, erection, use and dismantlingHSA scaffolds codeSite-specific risk/design, falls, falling materials, power, ground and public interface; competent technical review needed.
CSCS and inspection distinctionsHSA CSCS FAQ and HSA RAMS templateCurrent work category, GA3 and inspection frequency need specialist/date-of-work check.
RAMS and crew briefingHSA RAMS guidance and RAMS/SPoAWork-package plan plus task-level brief and active supervision.
Owner/cannibalisationUK scaffold RAMS page and UK guide are UK jurisdiction; IE construction owner is broadIrish fillable template provisionally distinct; repo/unpublished-draft owner check open.
Product/links/ie/construction observed; /ie/rams-software unverifiedNo invented design, automation, price or approval promise.
Copy/metadataDirect answer, substantial fillable method, holds, worked scenario, common failures, Irish sources and CTA boundaryREADY writer-side only; competent design, exact route, product and independent whole-page QA before publication.

Terminal writer-side disposition: READY. The responsible competent scaffolding contractor must adapt, approve and inspect the actual scaffold. No Complys site/repository content was changed.